Iranian Classification Society Rules

< Previous | Contents | Next >

SECTION 1 General


101. Application


1. This Annex apply to the drilling systems which or intended to be registered under the Society.


are installed on the unit classed with the Society


2. The requirements not specified in this Annex are to be in accordance with recognized national or international standards.


3. The following standards.


standards may be adequately referred as recognized national or international


Systems

Standard No.

Standard Title


Blowout Preventer (BOP) System

API Spec 6A

Specification for Wellhead and Christmas Tree Equipment

API Spec 16A

Specification for Drill-through Equipment


API Spec 16D

Control Systems for Drilling Well Control Equipment and Control Systems for Diverter Equipment

API RP 53

Blowout Prevention Equipment Systems for Drilling Operations

API RP 59

Recommended Practice for Well Control Operations


Lower Marine Riser Package (LMRP)

API Spec 16A

Specification for Drill-through Equipment


API Spec 16D

Control Systems for Drilling Well Control Equipment and Control Systems for Diverter Equipment

API Spec 16F

Specification for Marine Drilling Riser Equipment

API Spec 16R

Marine Drilling Riser Couplings


API PR 16Q

Design, Selection, Operation and Maintenance of Marine Drilling Riser Systems


Choke and Kill System

API Spec 6A

Specification for Wellhead and Christmas Tree Equipment

API Spec 16C

Choke and Kill Systems

API Spec 16F

Specification for Marine Drilling Riser Equipment

API RP 53

Blowout Prevention Equipment Systems for Drilling Operations

API RP 59

Recommended Practice for Well Control Operations


Diverter System


API Spec 16D

Control Systems for Drilling Well Control Equipment and Control Systems for Diverter Equipment

API Spec 6A

Specification for Wellhead and Christmas Tree Equipment

API RP 53

Blowout Prevention Equipment Systems for Drilling Operations

API RP 64

Recommended Practice for Well Control Operations


Auxiliary Well Control System

API Spec 7-1

Specification for Rotary Drill Stem Elements

API Spec 16A

Specification for Drill-through Equipment

API RP 53

Blowout Prevention Equipment Systems for Drilling Operations

image


Systems

Standard No.

Standard Title


Marine Drilling Riser System

API

Spec

16A

Specification for Drill-through Equipment


API


Spec 16Q

Design, Selection, Operation and Maintenance of Marine Drilling Riser Systems

API

Spec 16R

Marine Drilling Riser Couplings

API

Spec 16J

Comparison of Marine Drilling Riser Analyses

API

Spec 16F

Specification for Marine Drilling Riser Equipment


Hoisting, Lifting, Rotating and Pipe Handling System

API

Spec

7F

Oil Field Chain and Sprockets

API

Spec 7K

Specification for Drilling and Well Servicing Equipment

API

Spec 8A

Drilling and Production Hoisting Equipment


API


Spec 8C

Specification for Drilling and Production Hoisting Equipment (PSL 1 and PSL 2)

API

Spec 2C

Offshore Cranes

API

Spec 9A

Specification for Wire Rope


Derrick


API


Spec


4G

Recommended Practice for Use and Procedures for Inspection, Maintenance, and Repair of Drilling and Well Servicing Structures

API

Spec 4F

Drilling and Well Servicing Structures


Well Test System

API

Spec

6A

Specification for Wellhead and Christmas Tree Equipment

API

Spec 16C

Choke and Kill Systems

API

Spec 6D

Specification for Pipeline Valves


API


Spec 6AV1

Specification for Verification Test of Wellhead Surface Safety Valves and Underwater Safety Valves for Offshore Service


Materials


API


RP


2A-WSD

Planning, Designing and Working Stress Design

Constructing

Fixed

Offshore

Platforms

API

Spec 4F

Drilling and Well Servicing Structures


Piping

ASME B

31.3

Process Piping

API

Spec 16C

Choke and Kill Systems


API


Spec 16D

Control Systems for Drilling Well Control Equipment and Control Systems for Diverter Equipment


API


RP 14E

Recommended Practice for Design and Installation of Offshore Production Platform Piping Systems


102. Scope

This Annex covers the drilling system which includes the following. However items may differ ac- cording to type of units and is not limited to the following.

1. Well control system

(1) Blowout preventer (BOP) system

(2) Lower marine riser package (LMRP)

(3) Choke and kill system

(4) Diverter system

(5) Auxiliary well control system

2. Marine drilling riser system


3. Drill string compensation system


4. Mud and cementing system

(1) Bulk storage and transferring systems

(2) Mud circulating and mixing system

image

(3) Cementing system

image


5. Hoisting, lifting, rotating and pipe handling system


6. Derrick


7. Well test system


8. Burner booms


103. Equivalence and novel feature


1. Drilling systems which are not in compliance with this Annex may be acceptable provided that sat- isfactory service experience or a systematic analysis based on sound engineering principles demon- strate their overall safety and function.


2. Drilling systems which are not in compliance with this Annex may be acceptable provided that Systems are designed and constructed in accordance with recognized national standards or interna- tional standards.


3. The Society may consider the classification of systems based on or applying novel design principles or features, to which the Annex is not directly applicable, on the basis of experiments, calculations or other supporting information provided to the Society.


4. Risk evaluations may be applicable for the justification of alternative arrangements or novel features.


104. Design conditions

The drilling systems are to be designed to account erational, and test loads, or combination thereof.

1. Environmental conditions

(1) Earthquake

(2) Wind

(3) Ice

(4) Temperature

(5) Current, waves

(6) 1, 10, 50, 100 year storm event

2. Operational conditions

(1) Static pressure

(2) Vibration

(3) Transient pressure excursion


for all applicable following environmental, op-

(4) Acceleration loads due to movement

(5) Temperature excursion

(6) Retrieval

(7) Tension

(8) Bending

(9) Drifting

3. Transportation


4. Installation


5. Commissioning


6. Storage and maintenance


image

7. Test loads

of the unit

image